Progress of the Heavy Steel Workshop Construction at the Company
Release Date:
2013-11-18 12:53
As of November 6, the construction of Zhejiang Company’s 20,000‑ton‑per‑year heavy‑steel workshop has achieved significant interim milestones. According to the project team, the foundation works have successfully passed inspection by the municipal quality supervision authority. Steel components for the paint shop, as well as the north‑side steel columns and crane girders of the heavy‑steel workshop, have been erected; some columns have also undergone secondary grouting. The production layout and designated areas for equipment installation have been finalized, and the overall structural outline is now clearly visible.