Real-time updates on project progress—experience the Yuangong pace this passionate July.

Release Date:

2018-07-10 15:47

The construction site in July

The blazing sun scorches, and the summer heat is sweltering.

The palace attendants never slackened in their duties.

Forge brilliance with passion and sweat.

Forge brilliance with responsibility and commitment.

Latest Progress Report for Each Project

Presenting to you at this moment

 

 

 

 

Shandong Beichen Electromechanical Project

 

 

sdf

The Shandong Beichen Electromechanical Equipment and New Energy Production Base project is located within the Jinan Economic Development Zone. Constructed by Shandong Yuegong Steel Structure, the project has now successfully topped out its main structural framework. As a key provincial and municipal initiative and a flagship project for Changqing District, the Beichen project was selected as a sub‑venue for the first‑half‑year progress‑competition among Jinan’s counties and districts. On June 30, it received an inspection by city‑level leaders and earned high praise from officials at all levels as well as from industry peers.

The Beichen steel‑structure project has a total construction cost of over RMB 58 million, with a floor area of 45,000 square meters and an eave height of 16.5 meters. It comprises a six‑span factory building, featuring overhead cranes capable of lifting up to 260 tons. The project utilizes more than 4,700 tons of steel, with most steel columns requiring secondary assembly, secondary welding, and secondary shot blasting. The lattice columns, each weighing 18 tonnes, present exceptionally high technical challenges in both assembly and welding. Components began arriving on site on April 4. To ensure the successful completion of this project, the leadership team—including Chairman Luo Yinchang and General Manager Liu Qingli—attached great importance to its progress, convening multiple specialized meetings to coordinate the project schedule. Adhering to the corporate philosophy of “rigor and pragmatism, quality first, continuous improvement, and customer supremacy,” the company meticulously organized operations, tackled formidable challenges, and implemented comprehensive management measures, thereby ensuring the orderly advancement of the project and making due contributions to Shandong Province’s transformation of old and new growth drivers.

 

Guangxi Nanguo Copper Industry Project

 

sdf

This project comprises a multi‑storey steel‑structure factory building, with some sections extending to seven floors. It occupies a site area of 4,000 m² and utilizes a total of 2,820 tonnes of steel; the structural members predominantly consist of box‑section columns and H‑shaped steel beams.

The largest single box‑type column weighs 45 tonnes, stands 47 metres tall, features a large cross‑section and numerous corbels, and poses significant challenges in fabrication and installation. After thoroughly assessing transportation logistics and on‑site installation conditions, the Shandong Company adopted a well‑thought‑out segmental design during the detailed engineering phase, developed comprehensive technical plans for fabrication, transport, and on‑site erection, and conducted pre‑job technical briefings with all personnel, thereby ensuring the quality of both fabrication and installation at the site.

At present, the main structural work is undergoing large-scale installation, with completion scheduled for mid-August.

 

 

 

 

Central Asia Industrial and Trade Park, Zone B Project

 

sdaf

 

sdf

The project comprises a single-story light steel structure with a total floor area of 16,179.73 square meters. However, due to the client’s stringent schedule requirements, all fabrication and installation must be completed within 30 days to ensure commissioning and operation by early September. The project management team has developed a detailed, specialized construction plan and adopted a phased, zoned construction approach, making every effort to… While ensuring quality and safety, we also uphold the project schedule and our reputation. ! At present, the steel structure for Zone 1 has been largely installed, while in Zone 2, the installation of the supporting steel structures for equipment is well underway.

 

Chengdu Suning Project

 

sdf

The steel structure work for Warehouse No. 7 of the Chengdu B2C Automated Sorting Center Project (Phase II) covers a total floor area of 32,636.67 square meters. The project’s main steel structure and roof system have both been installed on schedule, and finishing work—including exterior and interior wall panels and canopies—is currently underway.